Fast, comprehensive refit adds significant value for blue chip
tennant
With a lease expiry looming, National Australa Bank secured 50
Miller St and embarked on a comprehensive Green Star fitout of 10
floors. To avoid costly lease penalties, our team commenced a
rigorous construction period, delivering eight floors in just
sixteen weeks. As an experienced Green Star fitout company, ISIS
managed all contractors, sourcing and documentation issues within
the narrow timeframe.
This project won an MBA NSW Award for Excellence.
Testimonial
"The project was critical in terms of both program and quality, without ISIS’ experience and collaborative approach we would not have achieved such a magnificent approach.”

Client: National Australia Bank
Floor Area: 10,000 m²
Delivery Model: Progressive Let, Lump Sum
Location: North Sydney
State: NSW
Project type: Fitout, Sustainability
Completion date: April 2008
Duration: 22 weeks, staged
Sustainability: Project targeted a 4 Star Green Star (Office Interiors v1.1) Certified Rating from the Green Building Council of Australia
Sector: Office