ALLIANCE BERNSTEIN, CHIFLEY TOWER, SYDNEY
Scope of Works
- 2100 square metre high quality corporate fitout over two levels
- Executive meeting floor with supporting kitchens and reception
- New internal staircases between levels 36 and 37
- Computer room is fully equipped with UPS, standalone air-conditioning, pre action fire services, and all critical systems are monitored both locally and internationally
- Complete audiovisual solution incorporating video conferencing systems
On Site Construction
- 3 weeks demolition and 12 weeks construction
Key Benefit Identified by Client
- ISIS' flexibility and understanding of client needs. Fast track and large scale changes were incorporated into the original program without impacting the project deadline.
» More Projects